XXXXXX仓储厂房工程高支模模板专项施工方案编 制:审 核:审 批:江苏 XX 建设集团有限公司2018 年 5 月 8 日一、工程概况·································11、项目基本情况:····························12、建筑设计概况:····························13、结构设计概况:····························24、高支模区域······························45、高支模区域地基情况··························46、高支模体系方案····························4二、编制依据·································6三、施工要求·································7四、技术保证条件·······························81、项目施工管理组织机构图及项目管理人员职责···············82、施工准备·······························92.1 施工现场准备···························92.2 技术准备·····························92.2 机具准备·····························92.3 材料准备····························102.4 材料力学性能指标························10五、施工段划分与施工进度计划························111、施工段划分:·····························112、施工进度计划:具体见 3#、4#、5#仓储厂房的总进度计划。········113、材料计划·······························114、测量及机具设备计划··························125、劳动力计划······························12六、施工方法及工艺·····························131、技术参数·······························132、工艺流程·······························133、主要施工方法·····························14七、模板、支撑排架拆除要求及成品保护····················241、模板拆除·······························242、支撑排架拆除·····························263、成品保护措施·····························27八、砼施工方法·······························281、 浇筑前的施工准备··························282、混凝土浇筑顺序····························303、浇筑要求和技术措施··························304、混凝土养护······························33九、模板检查、验收·····························34十、模板安全管理措施····························371、施工准备·······························372、施工组织管理机构···························38十一、模板安全技术措施···························391、脱模剂的选择及使用注意事项······················392、模板支撑施工····················...